Cledford

Value of project: 60K

Nature of works: Refurbishment of existing rooms and areas to form staff room. Forming new diasabled toilet. Community room. Enlarge and amend entrance hall and circulation area.

The works included the demolition of various internal walls, removing existing partitions, ceilings and floor finishes for the provision of new ceilings with intergrated lighting, new partitions and doors, new floor finishes, electrical services, data and fire alarm alterations and decorations on completion.

The project was a tight 16 day program and was completed 2 days early.